Electricity projects worth over 140 million Iraqi dinars will be implemented in Sulaimani
The Directorate of Electricity in Sulaimani is implementing several electricity projects in the city within a budget of 8%of electricity revenues, costing more than 140 million Iraqi dinars under the supervision of Sulaimani’s Electricity Distribution Directorate.
The projects include installing a 400 KVA transformer, an auxiliary transformer for Qul Qula village in Hawaii Star, 200+ feeder lines for Hawari Star station to deliver electricity to houses in Twaspi, a new transformer and lines in Bakrajo and Bakrajo stations, as well as 116 feeder lines around Sulaimani’s Electricity Distribution Directorate.
The total budget provided for the project is 140 million and 749 thousands Iraqi dinars and it will be implemented by Mizgin company, scheduled to be completed within 75 days.